Construction of a 500,000-gallon ground water storage tank at 643 9th Ave NW, Reform, AL including all site improvement items as shown in the plans and specifications.


Construction of a 500,000-gallon ground water storage tank at 643 9th Ave NW, Reform, AL including all site improvement items as shown in the plans and specifications.

The installation of approximately 2,280 linear feet of 12” PVC water main and associated fittings installed by open cut, one 16” HDPE Creek Crossing installed by direction drill, 2-12” ductile iron gate valves, connection to existing water main at each end of project, and all necessary appurtenances.

A proposed water transmission main, approximately 2,700 +/- L.F. of
20” HDPE water line, 140 +/- L.F. of 16” CL 51 Ductile Iron water line, valves, air release
valves, connection to systems and all necessary appurtenances in Calera, Alabama 35040.

Construction of a proposed sanitary sewer station, including submersible pumps, wet wells, SCADA, piping, valves, and all necessary appurtenances in Calera, Alabama 35040

Approximately 2,100 linear feet of 8” Ductile Iron water main installed by open cut with 54 linear feet of steel casing, approximately 100 linear feet of 8” ductile iron water main with steel casing installed by direct jack and bore, approximately 250 linear feet of DR11 10” HDPE installed by direction drill, 40 linear feet of 4” ductile iron water main installed by open cut, 16 linear feet of 4” ductile iron water main in 12” steel casing installed by jack and bore, three 8” gate valves, one 6” gate valve, one 4” gate valve, approximately 1,500 pounds of ductile iron fittings, one fire hydrant and assembly, and connection to existing water main, required erosion and sediment control, and all necessary appurtenances

A proposed water transmission main including base bid and alternates, up to approximately 20,380 +/- L.F. of 20” HDPE water line, 1,220 +/- L.F. of 16” DI water line, bore crossings, valves, air release valves, connection to systems and all necessary appurtenances in Calera, Alabama 35040.

Construction of a 1100 gpm backup production well, Snoddy Well No.2, at the site of existing Snoddy Well No.1 for increased supply capability and resiliency. Project activities also include the construction of a well canopy cover, configuration of piping, valves, and connections to the site’s existing treatment building, and electrical service upgrades to include all site improvement items as shown in the plans and specifications.

Identify and eliminate sources of infiltration and inflow within Carrollton’s wastewater collection system via video inspection, cleaning, de-rooting, installing cured-in-place pipe, cured-in-place manhole liners, manhole risers, and performing other sanitary sewer repairs.

Identify and eliminate sources of infiltration and inflow within Carrollton’s wastewater collection system via video inspection, cleaning, de-rooting, installing cured-in-place pipe, cured-in-place manhole liners, manhole risers, and performing other sanitary sewer repairs.

The expansion will include footings, concrete slab, building construction, and misc. other items as required to expand the current fire station.